单选题 在获取成功完成项目的活动中,项目团队喜欢互动和交流项目执行的故事,此时项目团队处于什么阶段?
In the event of successful completion of the project, the project team likes to interact and exchange project execution stories. What phase is the project team in?
单选题 项目团队由前军事和非军事小组成员组成。没有军事背景的团队成员认为前军事团队成员在他们的项目方法中过于结构化和僵化。前军事成员认为其他团队成员更随意的方式表明他们对该项目不太投入。什么样的工具或技术对项目经理和团队成员进行有效沟通最有用?
A project team is comprised of former military and non-military team members. The team members without a military background view the former military team members as overly structured and rigid in their approach to the project. The former military members view the other team members' more casual approach as an indication that they are less committed to the project. What tool or technique will be the most useful for the project manager and the team members to communicate effectively?
单选题 一个在瀑布式项目管理方法方面经验丰富的项目团队被分配到一个敏捷项目中。为了使转换更容易,已经决定保留瀑布方法的一些要素。在迭代审查期间,意识到开发团队之间的误解导致了工作的重复。项目经理如何处理这个问题?
A project team that is experienced in the waterfall project management approach has been assigned to their first agile project. To make the transition easier, it has been decided to keep some elements of the waterfall approach in placE.During the iteration review, it was realized that a misunderstanding among the development team has led to a duplication of efforts. How might the project manager address this issue?
单选题 根据项目的特点,项目经理建议选择一种敏捷方法,该方法限制团队成员在任何给定时间执行的任务数。此方法还允许团队提高工作过程中问题和瓶颈的可见性。项目经理建议采用以下哪种方法?
Based on the characteristics of the project, the project manager suggests selecting an agile method that limits the number of tasks being worked on by the team members at any given timE.This method will also allow the team to increase the visibility of issues and bottlenecks in their work process. Which of the following methods does the project manager suggest?
单选题 在项目执行阶段,生产经理要求项目经理包含一项已经证明可以显著提高产量的变更,项目经理首先应该做什么?
During a project's execution phase,the production manager asks the project manager to incorporate a change that has been proven to significantly increase output.What should the project manager do first?
单选题 在一个软件开发项目中,开发人员发现一个可以提高速度的新工具。项目经理分析发现这种新工具能够缩短当前开发阶段20%的时间,并节省10%的项目成本。在变更控制委员会批准之后,项目经理修订了项目进度。这属于哪种风险应对类型?
During a software development project, a developer discovers a new tool that could increase development speeD.The project manager’s analysis finds implementing the new tool could shorten the current development phase by 20% and save 10% of the project’s cost. After approval from the change control board, the project manager revises the project schedulE.What is the type of risk response?
单选题 一名新项目经理被任命管理一个正在执行的项目。针对这个项目,三天内将召开一次重要的里程碑核实会议。若要确保相应人员受邀参加会议,项目经理应该怎么做?
A new project manager is appointed to an ongoing project for which an important milestone validation meeting will occur in three days. What should the project manager do to ensure that the appropriate people are invited to this meeting?
单选题 项目落后于进度。项目团队发现,通过应用一个替代方法,他们可以加快关键路径上的一个项目可交付成果。然而,这将增加项目成本。项目经理应该怎么做?
A project is behind schedulE.The project team discovers that, by applying an alternate method, they may be able to expedite a project deliverable on the critical path. However, it will increase the project’s cost. What should the project manager do?