单选题 [单选] 两名项目团队成员一直对产品设计意见不一致。即使经过多次尝试,项目经理仍无法解决这个问题,项目现在落后于进度计划。项目经理应该是用什么冲突解决技术来立即解决这个问题?
Two project team members continually disagree on product design. Despite several attempts, the project manager is unable to resolve the issue, and the project is now behind schedule. What conflict resolution technique should the project manager use to immediately resolve this issue?

A、 缓和/包容
Smooth/accommodate
B、 妥协/调解
Compromise/reconcile
C、 撤退/回避
Withdraw/avoid
D、 强迫/命令
Force/direct
下载APP答题
由4l***a6提供 分享 举报 纠错

相关试题

单选题 [单选] 在最终测试阶段,新项目经理请求主题专家(SME)协助解决产品的一个紧急产量问题。应使用哪一项?
During the final testing phase, a new project manager requests assistance from subject matter experts (SMEs) to resolve an urgent yield issue with the project. What should be used?

A、专家判断
Expert judgment
B、石川图
Ishikawa diagram
C、质量管理计划
Quality management plan
D、控制图
Control chart

单选题 [单选] 在一个施工项目中,主题专家(SME)对如何识别材料方面的潜在项目风险持有不同意见。若要识别风险,项目经理应建议 SME 使用下列哪一项?
In a construction project, subject matter experts (SMEs) have differing opinions about how to identify potential project risks regarding construction materials. To identify the risks, the project manager should recommend that the SMEs use which of the following?

A、德尔菲技术
Delphi technique
B、头脑风暴法
Brainstorming
C、访谈
Interviewing
D、根本原因分析
Root cause analysis

单选题 [单选] 在一个施工项目中,项目经理识别到图表中的某些风险。如果所有三个风险全部发生,项目经理应请求多少额外资金?
Image.pngIn a construction project, the project manager identifies certain risks in the chart. How much additional funds should the project manager request if all three risks occur?

A、130,00 美元
130, 00 dollars
B、375,00 美元
375, 00 dollar
C、275,00 美元
275, 00 dollars
D、175,00 美元
175, 00 dollars

单选题 [单选] 项目开始时,项目发起人通知项目经理必须优先考虑成本控制。在规划期间,项目经理确定由外部供应商制造的部件需求明确,不大可能发生变化。项目经理应该对该供应商使用什么合同类型?
When the project starts, the project sponsor notifies the project manager that the cost control must be given priority. During the planning period, the project manager determines that parts manufactured by external suppliers are clearly required and unlikely to change. What type of contract should the project manager use for the supplier?

A、总价加激励费用合同(FPIF)
Fixed Price Incentive Fee Contract (FPIF)
B、成本加激励费用合同(CPIF)
Cost Plus Incentive Fee Contract(CPIF)
C、工料合同(T&M)
Time and Material Contract(T&M)
D、固定总价合同(FFP)
Firm Fixed Price Contract(FFP)

单选题 [单选] 在项目开始时,项目经理被要求准备一份快速、高层次成本估算。该项目经理之前从事过一个具有类似规模和复杂性的项目。项目经理应使用下列哪项工具或技术准备估算?
At the beginning of a project, a project manager is asked to prepare a quick, high-level cost estimate. The project manager previously worked on a project of similar size and complexity. What tools and techniques should the project manager use to develop the estimate?

A、三点估算和质量成本(COQ)
Three-points estimating and cost of quality (COQ)
B、卖方投标分析和群体决策技术
Vendor bid analysis and group decision-making techniques
C、专家判断和类比估算
Expert judgment and analogous estimating
D、自下而上估算和储备分析
Bottom-up estimating and reserve analysis

单选题 [单选] 一名项目团队成员未能按照沟通管理计划完成时间表。该团队成员没有这么做的正当理由。项目经理应该怎么做?
A project team member fails to complete timesheets in accordance with the communication management plan. The team member has no valid reason for this. What should the project manager do?

A、将问题上报给发起人。
Escalate it to the sponsor.
B、评估对项目进度计划的影响。
Evaluate the impact on the project schedule.
C、提醒该团队成员需要遵循正确的程序。
Remind the team member of the need to follow correct procedure.
D、委派另一名团队成员完成时间表。
Delegate another team member to complete the timesheets.

单选题 [单选] 在一次经验教训会议中,项目经理应记录哪项信息用于持续改进?
In a lessons learned meeting, what information should a project manager record for continuous improvement?

A、团队成员会议纪要
Team member’s meeting minutes
B、总成本和总预算
Total cost and budget
C、所做纠正措施原因
Reasons for corrective actions made
D、变更请求数量
Number of change requests

单选题 [单选] 软件开发项目的发起人很随意地通知项目经理,一个新沟通产品将很快在整个组织实施。项目经理应该怎么做?
The sponsor of a software development project casually informs the project manager communications product will soon be implemented across the organization. What should the project manager do?

A、更新沟通管理计划。
Update the communications management plan.
B、向项目相关方通知新产品。
Inform the stakeholders about the new product.
C、指示项目团队在新产品过程中发送项目更新信息。
Instruct the project team to send project updates through the new product.
D、等待接收正式通知。
Wait to receive formal notification.